The Planning and Reconstruction of the Bolshoi Theatre Complex started in the late nineties.
The New Stage of Bolshoi Theatre, Filial, was planned on the first Phase with the Main Auditorium with capacity of 900 seats, equipped with state-of-the-art Lighting and Mechanical systems.
The design phase started in 1998, with Mosproekt 2, Moscow.
The works on the Theatre technology implementation started in 2001.
The scope of work of Svetlost Teatar was the Design, Manufacturing, Supply, Installation of:
Stage Lighting System with Capacity: 1200 Dimmer channels 800 Luminaires 42 Light Curtains
Stage mechanical System:
1 Set, Fire Curtain, Fire protection devices
12 Motorized lighting towers below the stage’s lateral Galleries
71 Flybar field equipment and assembly
6 Lighting Battens field equipment and assembly
3 Flying mechanisms
Installation, mechanical and electrical work
Site Organization, Project Engineering
Opened to the public in October 2002